Overview
Client Helical
Role Project Management and Contract Administrator
Summary The works comprised of the reconfiguration of the
basement and ground floor for the installation of a new main entrance / reception, cafe, bike and shower facilities. Also, included was the conversion and fit out of units, installation of a main plant deck and external improvements.
Address 14 Gowers Walk, London, E1
Value £4.2 million (112,000 sq.ft)
Duration 68 weeks
Procurement/Tender Single Stage Lump Sum (Traditional)
Team Duggan Morris - Architect
GDM Partnership - Services Consultancy
Exigere - Quantity Surveyor
Heyne Tillett Steel – Structural Engineer
GVA – CDM Co-ordinator
Paragon - Main Contractor